Order No. GM Development HESCO Hyderabad NCB-09 Lot – I , Dated: 21-06-2012.
Client
Chief Engineer (Development) PMU
Location
Los Angeles, California
Started Year
21-06-2012.
Status
Completed
Contract Amount:
23.2 million
Contract Name:
Construction for Conversion of 66kV Grid Stations Matiari, KANDIARI and Naukot to 132kV Grid Stations Including Allied Civil Works, Transportation of Material to Site, Erection, testing and Commissioning of 132kV T/Lines IN & OUT feed for Matiari and KANDIARI and Noukot Grid Stations.